What must a CAN/ULC-S536-2019 report include?
Short answer
The Ontario Fire Code requires a record of each device, component and circuit that shows whether it is in proper working order, with the date and time of the test. Published summaries of the 2019 edition add measured values, a deficiency table that cites the clause, an attendance log and owner sign-off.
Edition: CAN/ULC-S536-2019Updated 2026-11-22Source: Ontario Fire Code, O. Reg. 213/07, on e-Laws
What does the Fire Code require in the record?
- 6.3.2.2.(4): a record of each device, component and circuit that is inspected and tested, showing whether it is in proper working order.
- 1.1.2.1.(1): the record notes what was done and the date and time it was done.
- 1.1.2.1.(3): records are kept at the building for the Chief Fire Official to examine.
- 1.1.2.1.(4): electronic records that can be made readily available on request are deemed to comply.
These come from the Ontario Fire Code as consolidated on e-Laws.
What do published summaries say the 2019 edition adds?
We have not reproduced the standard. Tap Report's comparison of the 2004 and 2019 editions lists these points:
- The report follows the standard's own template, with every section in order.
- A blank entry is treated as a deficiency. A section that does not apply is marked N/A.
- A checklist records the documents kept at the site.
- Deficiencies go in a table that cites the clause.
- The device list records measured values, not only pass or fail.
- An attendance log records names, dates and sign-in and sign-out times.
- The owner signs off after deficiencies are resolved, and the signed document is kept.
Check each point against your own copy of the standard.
What sections does a report have?
Our free template uses these 14 sections. The list follows the public descriptions above, not the text of the standard.
- Building, owner and system information
- Attendance log
- Site documentation checklist
- Control unit and transponders
- Power supplies and batteries
- Annunciators and remote trouble units
- Voice communication
- Field device record
- Circuit and data communication link tests
- Ancillary devices and interconnections
- Deficiencies
- Recommendations
- Technician declaration and signatures
- Owner sign-off
Who can carry out the annual inspection?
Sentence 6.3.2.1.(1) makes the owner responsible for using a person who meets Article 1.2.1.2 of Division C. That article requires a program or course acceptable to the Fire Marshal, and a certificate produced on request.
Sources
- Ontario Fire Code, O. Reg. 213/07, on e-Laws
- Tap Report: the difference between CAN/ULC-S536-04 and CAN/ULC-S536-19
Read on 2026-11-22. This page is a summary, not legal advice. The Fire Code and the standard govern.